Monday 8/13/2012


Weather: Rain then Sunny  84˚/58˚

Subs on Site
<TouchStone>              (16)
<Reliance>                    (3)
<Red Oak>                    (3)
<DG Concrete>            (5)

Work in Progress:
(TouchStone) Continued framing the 2nd floor walls.  Laid out the 3rd floor and started cutting the TJI's

(Reliance) Dug secondaries for Building 'C'

(Red Oak) formed Building 'B' garage footings

(DG Concrete) Prepped the Curb and gutter around Building 'C' and in front of Building 'D'.  They also graveled the slab for Building 'D'.  We found the center of road hubs at each end of the section of road were we are graded too deep.  The sub base was graded right on at each end.  The hub in the middle was a cut and as such was dug out.  Chris (DG Concrete) said go ahead with the curb and we will look at the road later.  DG Concrete also pointed out that the sewer clean out for Building 'D' is in the parking stalls and there was a lot of ground water when Ether (Red Oak Plumbing) hooked up the sewer lateral.