Subs on Site
<TouchStone> (16)
<Reliance> (3)
<Red Oak> (3)
<DG Concrete> (5)
Work in Progress:
(TouchStone) Finished framing the North end of the 2nd Floor. Rolled Joists on the South end and laid out the middle section.
(Reliance) Back filled the secondaries around Building 'C', delivered another conex and made ready to leave.
(Red Oak) Tied all the rebar in Building 'B' garage footings.
(DG Concrete) Finished the curb and gutter on the whole site. Installed the irrigation meters by Building 'D' and the Club house. We laid out the Club House footings. Tim and I laid out the drain boxes behind Building 'C' garage.