
Subs on Site
<TouchStone> (13)
<Reliance> (3)
<Red Oak Plumbing> (3)
<Red Oak> (9)
<DG Concrete> (5)
Work in Progress:
(TouchStone) Continued framing the 2nd floor walls and made up all of the headers they will need.. We discovered a problem with the decks were the concrete would only be 2" thick if we had full slope. We will now set the decks an 1 1/2" lower so the concrete will contain the slope.
(Reliance) Backfilled their trenches around Building 'C' and Fixed their conduit in front of Building 'D' that Ether (Red Oak Plumbing0 damaged.

(Red Oak Plumbing) Passed inspection on the underground in Building 'E' and started backfill
(Red Oak) poured the patios and breeze ways in Building 'C' Finished prep for the center section of Building 'C'. They also started setting forms on Building 'E' foundation walls.

