Weather: Sunny 93˚/59˚
Subs on Site
<TouchStone> (13)
<Reliance> (3)
<Red Oak Plumbing> (3)
<Red Oak> (9)
<DG Concrete> (5)

(Touchstone)Sheeted the 2nd floor. Finished the interior walls and sheeting on the 1st Floor.
(Reliance) Trenched for light poles and primaries around Building 'D'&'E' and pass inspection on the last of the light poles.
(Red Oak Plumbing) Plumbed Building 'D' inspection on Thursday

(Red Oak) Installed and passed inspection on Building 'C' slab rebar
(DG Concrete) finished graveling Building 'C', Graded for curb and gutter on the islands in Building 'A' parking lot, and started grading Building 'A' garage floor.