Subs on Site
<TouchStone> (13)
<Reliance> (3)
<Red Oak> (9)
(TouchStone) Continued framing the 2nd floor walls and cleaned the site.
(Reliance) worked on secondaries to Building 'C' and Building 'B'.
(Red Oak) poured the center section of Building 'C'. Pass inspection and poured the 1st half of Building 'E' foundation walls. Ben (Horrocks) told me they had a 7 1/2" slump.