Thursday 8/16/2012


Weather: Partly Cloudy  90˚/59˚

Subs on Site
<Sterns>                      (12)
<TouchStone>              (16)
<DG Concrete>            (3)

Work in Progress:


 (Sterns) Strung the curb in the areas were it could be slipped.  They do not have a form for Reverse Curb so they will Curb catch until the hand poured sections.  Dennis (Sterns) told me 1/2 after the curb is slipped you can walk on it and he would guarantee we could drive on it by Monday.

(TouchStone) continued sheeting 3rd floor joists and started 3rd Floor walls at the South end.  They also worked on the deck walls on the 2nd floor

(DG Concrete) finished the last parts of curb and gutter then repaired were Questar trenched along the curb and gutter at the North end of Building 'A'.  When (Sterns) showed up we walked he site and touched up the road so the curb machine would run smooth.  (Sterns) did not want to shove the roof drain pipes through were the machine slipped the curb.  I spoke with Keith (DG Concrete) and we decided to move as many of the drains to were (Sterns) was hand poring the curb and core out where we would have to.  Keith would work out the cost with McKay.