Wednesday 8/15/2012


Weather: Partly Cloudy  88˚/56˚

Subs on Site
<TouchStone>              (16)
<Red Oak>                    (3)
<DG Concrete>            (3)

Work in Progress:
(TouchStone) continued to roll the 3rd floor joists and started sheeting at the South end.

(Red Oak) passed inspection on Building 'B' garage footings.

(DG Concrete) dug and filled Club House footings.  Tim installed the gravel around my drain boxes behind Building 'C' garage.