Subs on Site
<TouchStone> (16)
<Red Oak> (3)
<DG Concrete> (3)
Work in Progress:
(TouchStone) continued to roll the 3rd floor joists and started sheeting at the South end.

(DG Concrete) dug and filled Club House footings. Tim installed the gravel around my drain boxes behind Building 'C' garage.