Monday 8/6/2012



Weather: Partly Cloudy/Rain  89˚/59˚

Subs on Site
<TouchStone>              (13)
<Reliance>                    (3)
<Red Oak Plumbing>   (2)
<Red Oak>                    (9)
<DG Concrete>            (5)



Work in Progress:
(Touchstone) rolled the joists for the middle and North section of Building 'A'.  Buttoned up the sheeting and interiors on the North end of Building 'A'

(Reliance) readied 6 light poles for inspection and pour tomorrow.

(Red Oak Plumbing) finished the last run of plumbing in Building 'C' after the fittings were delivered by Fed-Ex.  They cleaned up their back fill and moved down to Building 'D',  where Ether (Red Oak Plumbing) offered use of his mini-ex to speed the backfill.

(Red Oak) Poured Building 'E' footings, started forming Building 'B' garage footings, and tieing bar in Building 'C' floor.

(DG Concrete) Started back filling Building 'D'.  Charlie (Red Oak) asked that they final grade Building 'C' for his pour.  They graveled 1/2 of Building 'C'.  Ether (Red Oak Plumbing) let DG Concrete use his mini to finish back fill on Building 'D'.