Wednesday 8/8/2012


Weather: Sunny  93˚/57˚

Subs on Site
<TouchStone>              (13)
<Reliance>                    (3)
<Red Oak Plumbing>   (3)
<Red Oak>                    (9)
<DG Concrete>            (5)

Work in Progress:
(TouchStone) Started framing the 2nd floor walls and figured out the Stair holes.

(Reliance) Poured the last 4 light poles and continued with the primaries in front of Building 'C'

(Red Oak Plumbing) Installed the floor drains in Building 'C' before the 4 AM pour then finished plumbing Building 'D' and tested it.

(Red Oak) Pour each end of Building 'C' at 4 AM.  Then formed the breezeways and patios and started on 1/2 of Building 'E' foundation walls.

(DG Concrete) graded and graveled Building 'A' garage,  graded more curb and gutter, and graded Building 'C' garage.