Weather: Sunny 93˚/57˚
Subs on Site
<TouchStone> (13)
<Reliance> (3)
<Red Oak Plumbing> (3)
<Red Oak> (9)
<DG Concrete> (5)
Work in Progress:
(TouchStone) Started framing the 2nd floor walls and figured out the Stair holes.
(Reliance) Poured the last 4 light poles and continued with the primaries in front of Building 'C'
(Red Oak Plumbing) Installed the floor drains in Building 'C' before the 4 AM pour then finished plumbing Building 'D' and tested it.

(Red Oak) Pour each end of Building 'C' at 4 AM. Then formed the breezeways and patios and started on 1/2 of Building 'E' foundation walls.
(DG Concrete) graded and graveled Building 'A' garage, graded more curb and gutter, and graded Building 'C' garage.