Friday 6/29/2012

Weather: Sunny 97˚/62˚


Subs on Site
<RAM>                                       (2)
<Red Oak Plumbing>                  (1)
<Red Oak>                                  (7)

Work in Progress:
(RAM) Unloaded another load of lumber and continued to organize there Lumber Lot.

(Red Oak Plumbing)dug their first trenches and committed to inspection on Monday AM for the first half of Building 'A' underground.  It was decided that we will go ahead with Type 'B' units all the way up instead of the standard unit floor plan.


(Red Oak Concrete) pour the North Breeze way walls and the outer columns on the whole of Building 'A'.

Thursday 6/28/2012


 Weather: Sunny & Windy 94˚/59˚

Subs on Site
<RAM>                                       (2)
<Red Oak Plumbing>             (1)
<Red Oak>                                (7)
<DG Concrete>                         (4)

Work in Progress:
(RAM) Continued to arrange their lumber stacks and started installing their temp fence.  They gave me  the a key to the conex and fence.

(Red Oak) stripped the forms on the north end of Building 'A' and finished forming the north breeze way walls.  The inspection was schedule for Noon, I called at 1:00 and they had scheduled it for tomorrow.  This is the second time they have done this.  Mat (Inspector) came by around 3:00 and pass us.  We rescheduled the mud for 9:30 am tomorrow.


(DG Concrete) Conpacted the E-fill lift on the interior footings on the south end of Building 'A' and backed filled the interior to middle of Building 'A'.  They also started prepping the footings on Building 'D' &'E'.















Wednesday 6/27/2012

 Weather: Sunny & Windy 95˚/59˚


Subs on Site
<RAM>                                       (4)
<Red Oak Plumbing>             (1)
<Red Oak>                                (7)
<DG Concrete>                         (4)
<Horrocks>                               (1)

Work in Progress:
(RAM) started to set up their staging area and delivered a brand new forklift.

(Red Oak Plumbing) delivered a mini-ex on site.

(Red Oak Concrete) Finished forming the north section tall walls, passed inspection, and poured. I was told the pour would be at 2:00 PM and it did not start until 3:15.  Ron (Horrocks) had to wait. Then started forming the north breeze way walls.

(DG Concrete) Fixed the hydrant and poured a large thrust block behind it.  They passed inspection on Building 'C' garage footings and failed on Building  'B' garage footings.  Shad (DG Concrete) backfilled the southern end of Building 'A'.  Chris (DG Concrete) set all of the storm drain boxes.



Tuesday 6/26/2012


Weather Sunny & Windy 96˚/60˚


Subs on Site
<Red Oak>            (7)
<DG Concrete>      (4)

Work in Progress:
Wayne (Extreme Fire) met with Jeremy and Ryan (Fire Marshall) and conducted a flow test on the fire hydrants.



(Red Oak) Stripped forms South Breezeway walls and the East side of middle section.  Started tieing bar and forming for the north section.


(DG Concrete) Re-Compacted the footings on Building 'C' garage. Finished digging and filling footings on Building 'B' garage.  Chris (DG Concrete) Fire lane prep.  Jesse (DG Concrete) Backed off a 3 foot cliff with the water truck,  Chris (DG Concrete) told him he has to be aware of everything around him while operating equipment.  15 seconds later Jesse (DG Concrete) hit the fire hydrant.  Brandon (Maeser) came to collect a sample for the 2nd of 2 bacterial cultures on our water line.










Monday 6/25/2012


Weather Sunny & Windy 96˚/54˚


Subs on Site
<Red Oak>            (7)
<DG Concrete>      (4)
<Horrocks>            (1)

Work in Progress:
(Red Oak) Finished forming South Breezeway walls and the East side of middle section.  Inspected and poured.

(DG Concrete) Re-Compacted the footings on Building 'C' garage.  Compaction passed on all but one corner.  Started digging a filling footings on Building 'B' garage.  Chris (DG Concrete) started on fire lane prep.  (DG Concrete) added 3 yrds of concrete to (Red Oak's) pour for trust blocks.

I was unloading lumber until after 8 PM.







Friday 6/22/2012


Weather Sunny & Windy 96˚/54˚

Subs on Site
<Red Oak>            (7)
<Horrocks>            (1)


Work in Progress:
(Red Oak) Finished forming the west wall of the middle section of Building 'A'  Charlie (Red Oak) and I worked out the holddown bolts & window size and location's. Then they poured.


Thursday 6/21/2012


Weather Sunny & Windy 89˚/53˚


Subs on Site
<Red Oak>            (7)
<DG Concrete>      (2)

Work in Progress:
(Red Oak)Formed the far southern end of Building 'A' and 1/2 the west wall of the middle section.  Inspection passed.

(DG Concrete) Finish digging the footings for Building 'C's garage.  Ben (Horrocks) came to pick up his concrete cylinders and tested the compaction on the garage footings all tests failed.



Wednesday 6/20/2012


Weather Sunny & Windy 77˚/48˚

Subs on Site
<Red Oak>            (7)
<DG Concrete>      (2)
<Horrocks>            (1)


Work in Progress:

(Red Oak) Started striping forms from yesterdays footing pour,  Poured the footing on the north end of Building 'A', and Tied the bar for the walls on the south end.

Mat (HUD) came by for HUD draw inspection.

(DG Concrete) installed the water services for the ClubHouse and dug on the garage for Building 'C'.
Tim (DG Concrete) unloaded the lumber truck for Ram Builders.  (He only dropped one) 

Tuesday 6/19/2012


Weather Sunny & Windy 85˚/46˚


Subs on Site
<Red Oak>            (7)
<DG Concrete>      (3)
<Horrocks>            (1)


Work in Progress:

(Red Oak)Finished tieing the vertical rebar on the second half of Building 'A's footings.  The inspection I scheduled for this afternoon never happened.  I called and Uintah County had Thursday afternoon scheduled.   We set it up for tomorrow morning.  (Red Oak) Started their first pour.  The first half of Building 'A's footings are poured.

Ben (Horrocks) pulled cylinders on the pour.

(DG Concrete) set the fire riser in Building 'B' & 'D' and started on Building 'E'



Monday 6/18/2012


Weather Sunny & Breezy 95˚/54˚


Subs on Site
<Red Oak>            (5)
<DG Concrete>      (3)

Work in Progress:
(Red Oak) Tied the rebar in the second half of Building 'A'.  They had to wait for more forms to be delivered.  Charlie (Red Oak) sent us the submittal on the concrete mixes this morning.

(DG Concrete) Set the meters for Building 'A' and started on the fire riser for Building 'B'.  Dusty (Maser) came out to take the first of two water samples for the bacteria culture test.




Building 'A' southern UFER ground

Friday 6/15/2012


Weather Sunny & Breezy 88˚/53˚


Subs on Site
<Red Oak>            (6)

 Work in Progress:
(Red Oak) Inspection passed on the south half of Building 'A'

Charlie (Red Oak), Nick, and I met and came up with our best plan for concrete wall height on each building and sent it to Shaun(AE Uribia)

Thursday 6/14/2012




Weather Sunny & Breezy 88˚/53˚


Subs on Site
<Red Oak>            (7)
<DG Concrete>      (4)

 Work in Progress:

(Red Oak) finished tieing the rebar in the southern half of Building 'A's footings and started on tieing the Verts.  I scheduled a rebar inspection for tomorrow afternoon 6/15/2012.


(DG Concrete) finished the redig on building 'C's exterior footings to frost depth.  Then Shad (DG Concrete) and I laid out Building 'C's garage and he started on digging the footings.  Chris (DG Concrete) set the water meters and ran in the service  to Building 'A','C','D'&'B'.






Wednesday 6/13/2012


Weather Sunny & Breezy 88˚/51˚


Subs on Site
<Red Oak>            (6)
<DG Concrete>      (4)
<Horrocks>            (1)

Work in Progress:
(Red Oak) formed and installed rebar in the breezeway footings.  They stopped forming the column footings and are awaiting the final decision regarding the size and layout of the footing.


(DG Concrete) re dug the exterior wall section to below frost depth in the last section on Building 'A' over the fire riser trench.  They then repacked the south and west walls on Building 'A's Garage.  They also started re digging the same exterior wall sections for Building 'C'.  Chris (DG Concrete) preformed and past the pressure test on the water main.


 Ben (Horrocks) passed the re compaction on Building 'A's Garage and the entire water line including the lateral alone Building 'A'

  

Tuesday 6/12/2012


Weather Sunny & Windy 83˚/50˚


Subs on Site
<Red Oak>            (6)
<DG Concrete>      (3)

Work in Progress:
(Red Oak) expanded the footing on the north end of the building as per the foundation correction received today in RFI # 3.  (Red Oak) also formed the first of the four spot footings at 6'x6' as per RFI #4

(DG Concrete) re-dug and installed structural fill for the footings for the patio walls while they dug the spot footing pad for the columns at each end of the breezeway.  (DG Concrete) also installed the fire riser for Building 'A' as well as finishing the water laterals on Building 'C'&'B'.
(DG Concrete) charged and started the chlorine bake of the water main.









Monday 6/11/2012


Weather Sunny & Windy 73˚/45˚


Subs on Site
<Red Oak>            (7)
<DG Concrete>      (3)
<Horrocks>            (1)
    
Work in Progress:
Tim (DG Concrete) had to jump start the water truck.  The battery access panel is located under the door.  After it was started Tim (DG Concrete) jumped out and his foot caught on the open battery door and rolled his ankle.  He fell to the ground.  When he sat up against the truck he past out for a few seconds.  He has been limping all day and looked to still be in pain when he left tonight.

Chris (DG Concrete) installed fire riser to Building 'C' and set the water meters for Building 'D' & 'E'.  The then started digging the fire riser for Building 'A'

Shad (DG Concrete) re-dug the south and west wall of Building 'A's garage from 10-4:30.  He recycled the structural fill.  Then started digging the spot footing for the columns on Building 'A'.  The column footing were set below frost line and I noticed that the exterior wall footing was not.  Shad (DG Concrete) and I came up with at plan to fix the depth.   He pulled all of the the structural fill into the new column footing holes and then dug the wall down to below frost line.

 (Red Oak) laid out and formed the footings for Building 'A' and bent rebar.

I noticed damage to 2500 W on our south entrance ramp.(picture below)  It must have occured sometime between when I swept the road, Thursday 6/7/2012 and today.