Weather Sunny & Breezy 88˚/51˚
Subs on Site
<Red Oak> (6)
<DG Concrete> (4)
<Horrocks> (1)
Work in Progress:
(Red Oak) formed and installed rebar in the breezeway footings. They stopped forming the column footings and are awaiting the final decision regarding the size and layout of the footing.

Ben (Horrocks) passed the re compaction on Building 'A's Garage and the entire water line including the lateral alone Building 'A'