Wednesday 6/13/2012


Weather Sunny & Breezy 88˚/51˚


Subs on Site
<Red Oak>            (6)
<DG Concrete>      (4)
<Horrocks>            (1)

Work in Progress:
(Red Oak) formed and installed rebar in the breezeway footings.  They stopped forming the column footings and are awaiting the final decision regarding the size and layout of the footing.


(DG Concrete) re dug the exterior wall section to below frost depth in the last section on Building 'A' over the fire riser trench.  They then repacked the south and west walls on Building 'A's Garage.  They also started re digging the same exterior wall sections for Building 'C'.  Chris (DG Concrete) preformed and past the pressure test on the water main.


 Ben (Horrocks) passed the re compaction on Building 'A's Garage and the entire water line including the lateral alone Building 'A'