Weather Sunny & Breezy 88˚/53˚
Subs on Site
<Red Oak> (7)
<DG Concrete> (4)
Work in Progress:
(Red Oak) finished tieing the rebar in the southern half of Building 'A's footings and started on tieing the Verts. I scheduled a rebar inspection for tomorrow afternoon 6/15/2012.
(DG Concrete) finished the redig on building 'C's exterior footings to frost depth. Then Shad (DG Concrete) and I laid out Building 'C's garage and he started on digging the footings. Chris (DG Concrete) set the water meters and ran in the service to Building 'A','C','D'&'B'.