Weather Sunny & Windy 85˚/46˚
Subs on Site
<Red Oak> (7)
<DG Concrete> (3)
<Horrocks> (1)
Work in Progress:
(Red Oak)Finished tieing the vertical rebar on the second half of Building 'A's footings. The inspection I scheduled for this afternoon never happened. I called and Uintah County had Thursday afternoon scheduled. We set it up for tomorrow morning. (Red Oak) Started their first pour. The first half of Building 'A's footings are poured.
Ben (Horrocks) pulled cylinders on the pour.

(DG Concrete) set the fire riser in Building 'B' & 'D' and started on Building 'E'