Subs on Site
<Reliance> (3)
<Red Oak> (10)
Work in Progress:
(Reliance)pulled temp power to Building 'D' & 'E'
(Red Oak)Poured the southern 2/2 walls on Building 'B' then missed inspection on the Club House walls. I called and rescheduled for later. They passed inspection and poured the Club House walls.