Tuesday 9/25/2012

Weather: Rain 73˚/48˚

Subs on Site
<Utek>                         (11)
<Red Oak>                   (7)
<DG Concrete>            (2)

Work in Progress:
(Utek)Framed walls on the 4th floor 65% complete. Worked with Clegg Steel with their crane to set the stairs. And worked on interior walls and pick up for the 2nd Floor.

(Red Oak) Tied bar for the Club House and passed inspection


(DG Concrete) finished the parking lot for Building 'A'