Subs on Site
<Reliance> (3)
<Red Oak> (4)
<DG Concrete> (2)
Work in Progress:
(Reliance) pulled Primary to Building 'B' and Club House foundations and set a temp power panel for 'D' and dug trenches for Club house
(Red Oak)Formed Building 'B' breezeway Foundation
(DG Concrete) back filling Building 'B' garage floor and added gravel