Weather: Clear 82˚/49˚Subs on Site
<Sterns> (7)
<Reliance> (3)
<Red Oak> (8)
<DG Concrete> (2)
Work in Progress:
(Sterns) poured the tie ins around the sections of curb they slipped Friday
(Reliance) set transformer pads around Building 'A' & 'C'(Red Oak) Poured the Garage floor for Building 'C' and finished forming the Foundation wall for Building 'B' and started on the Club House footing
(DG Concrete) graveled 1/2 Building 'E' floor.