Tuesday 9/11/2012


Weather: Partly Cloudy  74˚/49˚

Subs on Site
<Sterns>                      (10)
<Reliance>                   (1)
<Red Oak>                  (6)
<DG Concrete>            (2)

Work in Progress:
(Sterns) formed and poured the dumpster pads

(Reliance)ran conduit into Club house before back fill

(Red Oak)Formed Building 'B' breezeway Foundation and passed inspections

(DG Concrete)back filling Club house floor touched up the dumpster footings and the parking sub base

I met with Paul (Utek) after they went over the material on site.  We discussed the trusses and where they will be putting the crane for each building.