Wednesday 9/5/2012


Weather: Clear  85˚/54˚

Subs on Site
<Reliance>                   (3)
<Red Oak>                  (8)
<DG Concrete>            (2)

Work in Progress:
(Reliance) set transformer pads around Building 'D' & 'E' and moved the sectionalizer out of the sidewalk by Building 'C'

(Red Oak) Poured 1/2 Building 'B' Foundation and the Club House footing

(DG Concrete) graveled 2/2 Building 'E' floor, fixed their mini's boom, and installed the road crossing for the landscaper.