Subs on Site
<Reliance> (3)
<Red Oak Plumbing> (4)
<DG Concrete> (2)
Work in Progress:
(Utek) delivered their work trailer and office equipment
(Reliance)Trenched for Strata along 2500 W
(Red Oak Plumbing) trenched for Building 'B' underground plumbing. Backfilled the Club House
(DG Concrete) Backfilled the 2nd half of Building 'B' floor and started installing E-fill in Building 'C' parking lot

![]() |
Shad (DG Concrete) hit electrical conduit |