Monday 9/24/2012

Weather: Partly Cloudy  73˚/48˚

Subs on Site
<Clegg Steel>               (3)
<Utek>                         (11)
<Red Oak>                   (7)
<DG Concrete>            (2)

Work in Progress:
(Clegg Steel) Installed stairs for the South West corner of Building 'A'

(Utek)Framed walls on the 4th floor 50% complete. Worked with Clegg Steel with their crane to set the stairs. And worked on interior walls and pick up for the 2nd Floor.

(DG Concrete) graveled the Club House and wet the E-fill material to get it ready to install in the road. Shad had to run to Indian Canyon with the mini because Brad was over weight with the rocks for the rock walls.