Thursday 9/20/2012


Weather: Sunny  77˚/47˚

Subs on Site
<Utek>                         (11)
<Red Oak Plumbing>    (5)
<Red Oak>                   (7)
<DG Concrete>            (2)

Work in Progress:
(Utek) delivered a second fork lift and a man basket.  Then started 4th floor Building 'A' walls. The also installed the 4th floor landings

(Red Oak Plumbing) passed inspection for underground in Building 'B' and started backfill

(Red Oak)Poured Building 'E' floor

(DG Concrete) started installing E-fill in East end of  Building 'A' parking lot.  Compaction Test passed on the South end.

For Nick