Subs on Site
<Utek> (8)
<Reliance> (3)
<Red Oak Plumbing> (4)
<Red Oak> (7)
<DG Concrete> (2)
Work in Progress:

(Reliance)laid the conduit for Strata along 2500 W and backfilled the trench. Installed the fire alarm loop in Building 'B' then loaded their equipment and left for Farmington.
(Red Oak Plumbing) installed underground in Building 'B'
(Red Oak) tied bar in Building 'B' garage floor.
(DG Concrete) started installing E-fill in West end of Building 'A' parking lot. Compaction Tests failed in Building 'C' parking lot. Too Dry.