Thursday 9/6/2012


Weather: Partly Cloudy  83˚/49˚

Subs on Site
<Reliance>                   (3)
<Red Oak>                  (10)
<DG Concrete>            (2)

Work in Progress:
 (Reliance) Vacuumed pull cord through their conduit.  Trenched from the light pole by the Playground to Building 'E' and repaired the conduit near the Club House.

(Red Oak)Formed 2/2 Building 'B' Foundation and passed inspection.

(DG Concrete) dug the foundations for the Dumpster pads and started back filling Building 'B' garage floor.