Friday 12/21/2012


Weather: Partly Cloudy  11˚/-5˚ 

Subs on Site
<Warburtons>                (4)
<Nutek>                          (14)
<Air Doctors>                  (5)
<Extreme Fire>               (3)
<Utek>                            (20)
<Reliance>                      (5)

Work in Progress:
(Warburtons) worked on siding for the North Breeze way. 

(Nutek) Hung Sheetrock on last of 3rd floor units.  Continued taping on 1st floor of Building 'A'

(Air Doctors) installed ducts on 3rd and 4th floor of Building 'A'

(Extreme Fire) worked on the attic system for Building 'A' North end.  Cut the sprinkler heads for 3rd floor Building 'A'.  I called Jeremy (Fire Marshal) and arranged for him to come on Saturday to inspect the attic system so we can hang Sheetrock on the 4th floor.

(Utek) Set roof sections on Building 'D' finished the sheer tie-ins and details on 4th floor of Building 'E'.  Built floor section for Building 'B'

(Reliance) wired all the exhaust fans and lights in the drops on 4th floor Building 'A'





Thursday 12/20/2012


Weather: Partly Cloudy  21˚/2˚ 

Subs on Site
<Warburtons>                (7)
<Nutek>                          (14)
<Air Doctors>                  (4)
<Extreme Fire>               (3)
<Utek>                            (20)
<Reliance>                      (5)
<Red Oak Plumbing>      (3)

Work in Progress:
(Warburtons) worked on siding for the North Breeze way and the siding and Soffit on the West center section of Building 'A'.  Finished dry-in on Building 'C'  

(Nutek) Hung Sheetrock on 3rd floor units.  Continued taping on 1st floor of Building 'A'

(Air Doctors) installed ducts on 3rd floor of Building 'A'

(Extreme Fire) worked on the attic system for Building 'A' North end.  Cut the sprinkler heads for 3rd floor Building 'A'

(Utek) Set roof sections on Building 'D' finished the sheer tie-ins and details on 4th floor of Building 'E'.  Built floor section for Building 'B'

(Reliance) Drilled and boxed on Building 'C'

(Red Oak Plumbing) Worked on the gas lines for the  West side of the 1st and 2nd floors Building 'C' 



Wednesday 12/19/2012

Weather: Partly Cloudy  22˚/2˚ 

Subs on Site
<Warburtons>                (9)
<Nutek>                          (14)
<Standard Builders>       (3)
<Air Doctors>                  (3)
<Extreme Fire>               (2)
<Utek>                            (20)
<Reliance>                      (5)
<Red Oak Plumbing>      (7)

Work in Progress:
(Warburtons) worked on siding for the North Breeze way and the siding and Soffit on the West center section of Building 'A'.  Installed house wrap on the North end of Building 'A'  

(Nutek) Hung Sheetrock on 2nd floor units.  Continued taping on 1st floor of Building 'A'

(Standard Builders) Installed hollow metal door slabs on Building 'A'

(Air Doctors) installed ducts on 3rd floor of Building 'A'

(Extreme Fire) worked on the attic system for Building 'A' North end.

(Utek) Worked on roof sections for Building 'D' and standing walls on Building 'E'.  Building 'B' 2nd floor sections.

(Reliance) drilled and boxed on Building 'C'

(Red Oak Plumbing) finished Building 'C' DWV and started assembling shower valves and working on water lines.


Tuesday 12/18/2012


Weather: SNOW 34˚/12˚  Weather Day

Subs on Site
<Warburtons>                (9)
<Nutek>                          (14)
<Air Doctors>                  (3)
<Extreme Fire>               (2)
<Utek>                            (20)
<Reliance>                      (5)
<Red Oak Plumbing>      (7)

Work in Progress:
(Warburtons) worked on siding for the North Breeze way and the siding and Soffit on the West center section of Building 'A'.  Installed house wrap on the North end of Building 'A' until the wind/snow made it unsafe to work in the man basket. 

(Nutek) Hung Sheetrock on 2nd floor units.  Continued taping on 1st floor of Building 'A'

(Air Doctors) Installed the remaining ducts on 2nd Floor and started on the South end of 3rd floor.

(Extreme Fire) worked on the attic system for Building 'A' North end.

(Utek) Started working on roof sections for Building 'D' and standing walls on Building 'E' but the snow was coming down to hard burring their tools as they worked.

(Reliance) Drilled and boxed on Building 'C' and passed inspection on all exterior panels for Building 'C','D','E' and the ClubHouse.

(Red Oak Plumbing) worked on DWV for Building 'C'







Monday 12/17/2012


Weather: Light snow 37˚/16˚

Subs on Site
<Warburtons>                (9)
<Nutek>                          (12)
<Extreme Fire>               (2)
<Utek>                            (20)
<Reliance>                      (5)
<Red Oak Plumbing>      (7)

Work in Progress:
(Warburtons) worked on siding for the North Breeze way and the siding and Soffit on the West center section of Building 'A'.  Continued drying in Building 'C'.

(Nutek) Hung Sheetrock on 2nd floor units.  Continued taping on 1st floor of Building 'A'

(Extreme Fire) worked on the attic system for Building 'A' North end.

(Utek) framed the last of the drops on Building 'A' 3rd floor.  Set and framed on the Steel gables for Building 'C'.  Stood walls on Building 'E' and pre-fabbed floor sections for Building 'B'.

(Reliance) drilled and boxed on 2nd, 3rd, and 4th floors of Building 'C'

(Red Oak Plumbing) set the Tubs and ran DWV on 3rd floor of Building 'C'

Sub Meeting  12/10/2012
Alma (Utek)
William (Air Doctors)
Craig (Red Oak)
Jose (Warburtons)
Eric (Nutek)

Talking Points

  1. (Air Doctors) will finish ducts on 2nd floor today, 4th floor tomorrow,  3rd floor Wednesday or Thursday.  They will also finish the fire caulk for inspection tomorrow.
  2. Framers will finish framing drops tonight.
  3. (Extreme Fire) will finish the Attic system by end of day Tuesday 12/18 so that drywall can be hung on the 4th floor.  Drywall can hang all but the North breeze way and Northern 2 units.
  4. (Red Oak) Will finish tubs and DWV for inspection on Thursday 12/20.  Gas lines will start Thursday and 1st and 2nd floors will be complete by Thursday 12/27.
  5. (Nutek) will have ½ of 1st floor ready for finish carpenters by Thursday 12/20.
  6. In the 1x1 exterior units for Building ‘C’ 4th floor we will end the drop at the edge of the bedroom door in order to clear the attic access.  William (Air Doctors) said that it  will mean that the duct will end in the end of the drop and not down through the drop but that should not be a problem.  Shawn (Extreme Fire) said that Fire sprinklers should not need to change.

Schedule

Building ‘A’ Finish work starts 1st floor       1/2
Building ‘A’ Paint starts 1st floor               1/4

Building ‘A’ Gypcrete                   12/27-12/30

Building ‘C’  DWV inspection                   12/20
Building ‘C’  1st and 2nd  Floor 4-way                12/27

Friday 12/14/2012

Weather: Snow 35˚/25˚

Subs on Site
<Warburtons>                (9)
<Nutek>                          (10)
<Extreme Fire>               (2)
<Utek>                            (22)
<Reliance>                      (4)
<Red Oak Plumbing>      (5)

Work in Progress:
(Warburtons) worked on siding for the South Breeze way and the siding and soffit on the West center section of Building 'A'.  Continued drying in Building 'C'.

(Nutek) Hung Sheetrock on the 7th of the 8 1st floor units. Hung the 4th floor breeze way lids until Extreme Fire stopped them on the North End because they had not finished their attic system.  Fire taped 3rd floor units.  Taped pre rock behind the tubs on Building 'C'

(Extreme Fire) Worked on the attic system on Building 'A' and tested the 1st and 2nd floors for frost damage with compressed air.

(Utek) framed drops on 4th Floor of Building 'A'.  Framed backing around the 4th floor chase ceilings. Set the first entry gable and stared framing the roof on it.  Finished shear tie ins on 4th floor of Building 'D'.  Prepped to set walls on 4th floor Building 'E'.  Continued pre fab on Building 'B' 2nd Floor sections.

(Reliance) Drilled and boxed on Building 'C'

(Red Oak Plumbing) worked on DWV in Building 'C' Fire caulking as the go.

Thursday 12/13/2012


Weather: Clear 38˚/17˚

Subs on Site
<Warburtons>                (9)
<Nutek>                          (8)
<Diamond Z>                  (1)
<Extreme Fire>               (2)
<Utek>                            (22)
<Reliance>                      (4)
<Red Oak Plumbing>      (5)

Work in Progress:
(Warburtons) worked on siding for the South Breeze way and the siding and soffit on the West center section of Building 'A'.  Started drying in Building 'C'.

(Nutek) Hung sheetrock on the 6th of the 8 1st floor units.  Continued pre rock behind the tubs on Building 'C'

(Diamond Z) poured the grout for the top of the stone columns and cleaned up.

(Extreme Fire) worked on the attic system and cut he sprinkler heads that were already sheetrocked into the drops on Building 'A'

(Utek) Finished 2nd Floor drops. Installed the solid backing around all the chases in Building 'C'. Installed straps and sheer tie ins on Building 'D'. And started pre fabing Building 'B's 2nd Floor.  Paul agreed to have the drops on Building 'A' done this weekend.

(Reliance) driled, boxed and pulled low voltage in Building 'C'

(Red Oak) Ran the DWV in the center demising wall so that Nutek could pre Rock behind the tubs.



Wednesday 12/12/2012


Weather: Clear 38˚/17˚

Subs on Site
<Warburtons>                (9)
<Nutek>                          (5)
<Diamond Z>                  (1)
<Extreme Fire>               (2)
<Air Doctors>                 (1)
<Utek>                            (17)
<Reliance>                      (4)
<Red Oak Plumbing>      (6)

Work in Progress:
(Warburtons) worked on siding for the South Breeze way and the sidiing and soffit on the West center section of Building 'A'.  Finished up some roofing on Building 'A's peak.

(Nutek) Hung sheetrock on the 5th of the 8 1st floor units.  Started pre rock behind the tubs on Building 'C'

(Diamond Z) worked on the caps for the entry gables

(Extreme Fire) worked on the Attic system for Building 'A' and cut the sprinklers in the drop areas to the correct length.

(Air Doctors) touched up the fire caulk were needed for inspection.

(Utek)finished the roof on Building 'C'.  Worked on the pick-up sheeting for Building 'A' and started the drops on the 2nd Floor.  Finished standing the walls on Building 'D'.  Finished Sheeting the floor on Building 'E'.

(Reliance)started boxing and drilling on 1st floor Building 'C'

(Red Oak) set 4 of the tubs on first floor of Building 'C'.  Drilled for gas on Building 'C' and started stacking the DWV. 

Tuesday 12/11/2012


Weather: Partly Cloudy 38˚/16˚

Subs on Site
<Cardalls>                      (3)
<Warburtons>                (9)
<Nutek>                          (4)
<Diamond Z>                  (1)
<Extreme Fire>               (2)
<Air Doctors>                 (3)
<Utek>                            (17)
<Reliance>                      (4)
<Red Oak Plumbing>      (6)

Work in Progress:
(Cardalls) Insulated the walls behind the tubs and chases on Building 'C'

(Warburtons) Installed the siding and soffit on the South West corner of Building 'A' as well as the South Breezeway.  Roofed Building 'A' Garage.

(Nutek) Finished hanging the 1st floor units on the South end of Building 'A' and started on the North end.

(Diamond Z) Grouted the last of the stone on the Chimneys and started laying the caps stones for he entry columns on Building 'A'

(Extreme Fire) Worked on the attic system on the North End of Building 'A'.  Shawn (Extreme Fire) decided last night that we will be OK to keep going covering he fire sprinklers.

(Air Doctors) Ran exhaust Vents on Building 'C"

(Utek)finished Building 'C" roof, Started setting windows on Building 'C. Set wall sections for the 4th floor on Building 'D' and sheeted the 4th Floor on Building 'E'.  They also moved their crane from Building 'C' to Building 'D'.

(Reliance) worked on Building 'C" panels 





Monday 12/10/2012

Weather: Light snow 28˚/10˚

Subs on Site
<Cardalls>                      (3)
<Warburtons>                (6)
<Nutek>                          (4)
<Diamond Z>                  (1)
<Extreme Fire>               (2)
<Air Doctors>                 (3)
<Utek>                            (17)
<Reliance>                      (2)
<Red Oak Plumbing>      (1)

Work in Progress:
(Cardalls)Insulated the walls and ceilings on the North end of 3rd Floor for Building 'A' and finished the demising walls on 3rd and 4th floor.

(Warburtons) siding South breezeway and Soffit on Building 'A'. 

(Nutek) hung on the South end of 1st floor of Building 'A'.

(Diamond Z)Cleaned up their masking on Building 'A'

(Extreme Fire) worked on the attic system for Building 'A'.  They also discovered that the 1st and 2nd Floor sprinklers have frozen.  We need to defrost the system and retest for pressure.

(Air Doctors) assembled all the parts for running their flex duct once the drops are framed

(Utek) Finished framing the roof on Building 'C' and started hanging windows and doors on Building 'C' I did not tell them that we had opposite slides on the doors and the first floor was hung wrong.

(Reliance) pulls feeders to Building 'C' Panels.

(Red Oak Plumbing) fire caulked 2nd floor again and failed again.

Sub Meeting  12/10/2012
Jesse (Utek)
(Air Doctors)
Roy (Red Oak)
Doug (Cardalls)
Hose (Warburtons)

Talking Points

  1. The Fire sprinkler pipes froze on 1st and 2nd floor.  We need to thaw and re test.  Wednesday.  This will slow drywall even further.
  2. Framers will start drops Wednesday 12/12  morning.
  3. Warburtons will be done with Building ‘A’ roof on Wednesday by Noon
  4. Rob (Clegg Steel) will have steel for Buildings ‘D’ & ‘E’ steel and stairs on Monday 12/17
  5. (Red Oak) wants to start setting the tubs in Building ‘C’ (Nutek) will start hanging the pre-rock Wednesday.  I need to get heat for the firetape.
  6. (Air Doctors) will be running their vents in the chases on Building ‘C’ this weekend.
  7. 2nd, 3rd, and 4th  Floors of Building ‘A’ ready for drops to be framed.
  8. Final 4-way inspection notes  
    1. Fire caulk all ceiling penetrations (Romex, drains & fire sprinklers)
    2. Fire caulk all penetrations into exterior walls (Vents & Linesets)
    3. Plug the holes under the tubs on Building ‘A’ for gypcrete.
    4. 2nd Floor corridor ceiling needs to be re inspected (Nutek) will pull down the drywall on each side for re inspection.



Schedule
Final 4-way
2nd Floor     Tuesday    12/11
4th Floor Monday 12/11
3rd Floor    Thursday   12/12

Thursday 12/6/2012


Weather: Partly Cloudy 49˚/23˚

Subs on Site
<Cardalls>                      (3)
<Warburtons>                (12)
<Nutek>                          (9)
<Diamond Z>                  (3)
<Extreme Fire>               (5)
<Air Doctors>                 (2)
<Utek>                            (17)
<Reliance>                      (6)
<Red Oak Plumbing>      (7)

Work in Progress:
(Cardalls)Insulated the walls and ceilings on the North end of 3rd Floor for Building 'A' and above pre-rock on the North end of 3rd floor.

(Warburtons) siding South breezeway and Soffit on Building 'A'. Siding on Building 'B' garage. Worked on the last of Building 'A' roof and Building 'C' garage roof.

(Nutek) hung the pre-rock on 3rd floor, fire taped the pre- rock on 4th floor and hung the breeze way ceilings

(Diamond Z) stoned the chimneys on Building 'A'

(Extreme Fire) worked on the attic system for Building 'A' and the sprinklers on 3rd and 4th floor of Building 'A'

(Air Doctors) ran the ducts that are not mounted in the drops in the 2nd floor Building 'A'.

(Utek)finished setting the gables at the breezeways on Building 'C', wrapped up walls on the 3rd floor of Building 'D', and pre-fabbed floor sections for 4th floor of Buildings 'D' & 'E'

(Reliance) pull the feeders to the interior Panels on Building 'C'

(Red Oak Plumbing) drilled for DWV in Building 'C' and Labeled the gas lines for Questar.