Subs on Site
<Warburtons> (9)
<Nutek> (10)
<Extreme Fire> (2)
<Utek> (22)
<Reliance> (4)
<Red Oak Plumbing> (5)
Work in Progress:
(Warburtons) worked on siding for the South Breeze way and the siding and soffit on the West center section of Building 'A'. Continued drying in Building 'C'.
(Nutek) Hung Sheetrock on the 7th of the 8 1st floor units. Hung the 4th floor breeze way lids until Extreme Fire stopped them on the North End because they had not finished their attic system. Fire taped 3rd floor units. Taped pre rock behind the tubs on Building 'C'
(Extreme Fire) Worked on the attic system on Building 'A' and tested the 1st and 2nd floors for frost damage with compressed air.
(Utek) framed drops on 4th Floor of Building 'A'. Framed backing around the 4th floor chase ceilings. Set the first entry gable and stared framing the roof on it. Finished shear tie ins on 4th floor of Building 'D'. Prepped to set walls on 4th floor Building 'E'. Continued pre fab on Building 'B' 2nd Floor sections.
(Reliance) Drilled and boxed on Building 'C'
(Red Oak Plumbing) worked on DWV in Building 'C' Fire caulking as the go.
(Extreme Fire) Worked on the attic system on Building 'A' and tested the 1st and 2nd floors for frost damage with compressed air.
(Utek) framed drops on 4th Floor of Building 'A'. Framed backing around the 4th floor chase ceilings. Set the first entry gable and stared framing the roof on it. Finished shear tie ins on 4th floor of Building 'D'. Prepped to set walls on 4th floor Building 'E'. Continued pre fab on Building 'B' 2nd Floor sections.
(Reliance) Drilled and boxed on Building 'C'
(Red Oak Plumbing) worked on DWV in Building 'C' Fire caulking as the go.