Weather: SNOW 34˚/12˚ Weather Day
Subs on Site
<Warburtons> (9)
<Nutek> (14)
<Air Doctors> (3)
<Extreme Fire> (2)
<Utek> (20)
<Reliance> (5)
<Red Oak Plumbing> (7)
Work in Progress:
(Warburtons) worked on siding for the North Breeze way and the siding and Soffit on the West center section of Building 'A'. Installed house wrap on the North end of Building 'A' until the wind/snow made it unsafe to work in the man basket.
(Nutek) Hung Sheetrock on 2nd floor units. Continued taping on 1st floor of Building 'A'
(Air Doctors) Installed the remaining ducts on 2nd Floor and started on the South end of 3rd floor.
(Air Doctors) Installed the remaining ducts on 2nd Floor and started on the South end of 3rd floor.
(Extreme Fire) worked on the attic system for Building 'A' North end.
(Utek) Started working on roof sections for Building 'D' and standing walls on Building 'E' but the snow was coming down to hard burring their tools as they worked.
(Reliance) Drilled and boxed on Building 'C' and passed inspection on all exterior panels for Building 'C','D','E' and the ClubHouse.
(Red Oak Plumbing) worked on DWV for Building 'C'
(Reliance) Drilled and boxed on Building 'C' and passed inspection on all exterior panels for Building 'C','D','E' and the ClubHouse.
(Red Oak Plumbing) worked on DWV for Building 'C'