Subs on Site
<Cardalls> (3)
<Warburtons> (6)
<Nutek> (6)
<Diamond Z> (3)
<Extreme Fire> (5)
<Air Doctors> (3)
<Clegg Steel> (4)
<Utek> (21)
<Reliance> (3)
<Red Oak Plumbing> (5)
Work in Progress:
(Cardalls)Insulated the walls on the 2nd Floor for Building 'A'.
(Warburtons) siding on both sides of the center section of Building 'A'. Installed the house wrap in the breezeways and finished the siding on Building 'A' garage.
(Nutek) Hung drywall in Building 'A' garage. Fire taped the pre-rock on 2nd floor Building 'A'
(Diamond Z) wrapped up some odds and end on the North end of Building 'A'
(Extreme Fire) worked on the attic system and the side wall sprinklers for 3rd and 4th floors of Building 'A'
(Air Doctors) installed their hard duct on 2nd floor Building 'A'
(Clegg Steel) installed the stairs on 1st floor of Building 'C'
(Utek) framed 1st floor on Building 'B'. Set floor sections Building 'E'. Wrapped up all they could on Building 'C' roof without having he Steel columns installed.
(Reliance) set the exterior panels on Building 'D' and 'E'
(Red Oak Plumbing) set the Tubs on Building 'C'. They did not finish the fire caulk North half of 3rd floor on Building 'A' so we failed the re-inspection. They had fire caulk to finish on 1st floor as well. They did not fire caulk the ADA tubs and will now have to remove them and start over.
(Nutek) Hung drywall in Building 'A' garage. Fire taped the pre-rock on 2nd floor Building 'A'
(Diamond Z) wrapped up some odds and end on the North end of Building 'A'
(Extreme Fire) worked on the attic system and the side wall sprinklers for 3rd and 4th floors of Building 'A'
(Air Doctors) installed their hard duct on 2nd floor Building 'A'
(Clegg Steel) installed the stairs on 1st floor of Building 'C'
(Utek) framed 1st floor on Building 'B'. Set floor sections Building 'E'. Wrapped up all they could on Building 'C' roof without having he Steel columns installed.
(Reliance) set the exterior panels on Building 'D' and 'E'
(Red Oak Plumbing) set the Tubs on Building 'C'. They did not finish the fire caulk North half of 3rd floor on Building 'A' so we failed the re-inspection. They had fire caulk to finish on 1st floor as well. They did not fire caulk the ADA tubs and will now have to remove them and start over.