Thursday 12/6/2012


Weather: Partly Cloudy 49˚/23˚

Subs on Site
<Cardalls>                      (3)
<Warburtons>                (12)
<Nutek>                          (9)
<Diamond Z>                  (3)
<Extreme Fire>               (5)
<Air Doctors>                 (2)
<Utek>                            (17)
<Reliance>                      (6)
<Red Oak Plumbing>      (7)

Work in Progress:
(Cardalls)Insulated the walls and ceilings on the North end of 3rd Floor for Building 'A' and above pre-rock on the North end of 3rd floor.

(Warburtons) siding South breezeway and Soffit on Building 'A'. Siding on Building 'B' garage. Worked on the last of Building 'A' roof and Building 'C' garage roof.

(Nutek) hung the pre-rock on 3rd floor, fire taped the pre- rock on 4th floor and hung the breeze way ceilings

(Diamond Z) stoned the chimneys on Building 'A'

(Extreme Fire) worked on the attic system for Building 'A' and the sprinklers on 3rd and 4th floor of Building 'A'

(Air Doctors) ran the ducts that are not mounted in the drops in the 2nd floor Building 'A'.

(Utek)finished setting the gables at the breezeways on Building 'C', wrapped up walls on the 3rd floor of Building 'D', and pre-fabbed floor sections for 4th floor of Buildings 'D' & 'E'

(Reliance) pull the feeders to the interior Panels on Building 'C'

(Red Oak Plumbing) drilled for DWV in Building 'C' and Labeled the gas lines for Questar.