Tuesday 12/4/2012

Weather: Sunny 47˚/25˚

Subs on Site
<Cardalls>                      (3)
<Warburtons>                (12)
<Nutek>                          (6)
<Diamond Z>                  (3)
<Extreme Fire>               (5)
<Air Doctors>                 (3)
<Clegg Steel>                 (4)
<Utek>                            (21)
<Reliance>                      (3)
<Red Oak Plumbing>      (4)

Work in Progress:
(Cardalls)Insulated the ceilings on the 3rd Floor for Building 'A' and the walls 

(Warburtons) siding on both sides of the center section of Building 'A'. Finished the house wrap in the breezeways and put house wrap on Building 'B' garage.   

(Nutek) Hung drywall in Building 'A' garage and started 4th floor pre-rock on Building 'A'

(Diamond Z) Worked on Building 'A' stone and Chimneys

(Extreme Fire) worked on the attic system for Building 'A'. And fire sprinklers for Building 'C'

(Air Doctors) installed the hard ducts on the 2nd floor of Building 'A' and worked on the line sets for Building 'C'.

(Clegg Steel) Installed the stairs on the 1st and half of the 2nd floor on the West end of Building 'C' on the wrong side of the breezeway.  They cut them out and re installed them.

(Utek) flashed all the windows for Building 'C'. Started setting the steel columns on Building 'C'.  Finished framing the walls on 1st floor of Building 'B'.  Started setting wall sections on the 3rd floor of Building 'D' and started sheeting the 3rd floor of Building 'E'.

(Reliance) Worked on the panels for the Garages and started setting interior Panels for Building 'C'

(Red Oak Plumbing) Fire caulked 3rd floor and 1st floor pre-rock.  As well as working on a fix for the ADA tubs.