Subs on Site
<Cardalls> (2)
<Warburtons> (6)
<Nutek> (3)
<Diamond Z> (4)
<Extreme Fire> (5)
<Air Doctors> (4)
<Utek> (19)
<Red Oak Plumbing> (5)
Work in Progress:
(Cardalls)Insulated the walls on the 2nd Floor for Building 'A'.
(Warburtons) siding on both sides of the center section of Building 'A'
(Nutek) Pre-rocked units on the North end of 2nd floor on Building 'A'
(Diamond Z) stoned the columns on the North East corner of Building 'A'
(Air Doctors) started running their ducts on 1st floor of Building 'A'
(Utek) Sheeted Building 'C' roof. Sheeted the floor on Building 'D'. Framed the lower walls on Building 'B'.
(Red Oak Plumbing) etched the numbers on the gas lines so we can install the meters on Monday. Worked on the water lines for the North end of 3rd and 4th floors of Building 'A'.
(Red Oak Plumbing) etched the numbers on the gas lines so we can install the meters on Monday. Worked on the water lines for the North end of 3rd and 4th floors of Building 'A'.