Wednesday 12/19/2012

Weather: Partly Cloudy  22˚/2˚ 

Subs on Site
<Warburtons>                (9)
<Nutek>                          (14)
<Standard Builders>       (3)
<Air Doctors>                  (3)
<Extreme Fire>               (2)
<Utek>                            (20)
<Reliance>                      (5)
<Red Oak Plumbing>      (7)

Work in Progress:
(Warburtons) worked on siding for the North Breeze way and the siding and Soffit on the West center section of Building 'A'.  Installed house wrap on the North end of Building 'A'  

(Nutek) Hung Sheetrock on 2nd floor units.  Continued taping on 1st floor of Building 'A'

(Standard Builders) Installed hollow metal door slabs on Building 'A'

(Air Doctors) installed ducts on 3rd floor of Building 'A'

(Extreme Fire) worked on the attic system for Building 'A' North end.

(Utek) Worked on roof sections for Building 'D' and standing walls on Building 'E'.  Building 'B' 2nd floor sections.

(Reliance) drilled and boxed on Building 'C'

(Red Oak Plumbing) finished Building 'C' DWV and started assembling shower valves and working on water lines.