Thursday 12/13/2012


Weather: Clear 38˚/17˚

Subs on Site
<Warburtons>                (9)
<Nutek>                          (8)
<Diamond Z>                  (1)
<Extreme Fire>               (2)
<Utek>                            (22)
<Reliance>                      (4)
<Red Oak Plumbing>      (5)

Work in Progress:
(Warburtons) worked on siding for the South Breeze way and the siding and soffit on the West center section of Building 'A'.  Started drying in Building 'C'.

(Nutek) Hung sheetrock on the 6th of the 8 1st floor units.  Continued pre rock behind the tubs on Building 'C'

(Diamond Z) poured the grout for the top of the stone columns and cleaned up.

(Extreme Fire) worked on the attic system and cut he sprinkler heads that were already sheetrocked into the drops on Building 'A'

(Utek) Finished 2nd Floor drops. Installed the solid backing around all the chases in Building 'C'. Installed straps and sheer tie ins on Building 'D'. And started pre fabing Building 'B's 2nd Floor.  Paul agreed to have the drops on Building 'A' done this weekend.

(Reliance) driled, boxed and pulled low voltage in Building 'C'

(Red Oak) Ran the DWV in the center demising wall so that Nutek could pre Rock behind the tubs.