Weather: Light snow 37˚/16˚
Subs on Site
<Warburtons> (9)
<Nutek> (12)
<Extreme Fire> (2)
<Utek> (20)
<Reliance> (5)
<Red Oak Plumbing> (7)
Work in Progress:
(Warburtons) worked on siding for the North Breeze way and the siding and Soffit on the West center section of Building 'A'. Continued drying in Building 'C'.
(Nutek) Hung Sheetrock on 2nd floor units. Continued taping on 1st floor of Building 'A'
(Extreme Fire) worked on the attic system for Building 'A' North end.
(Utek) framed the last of the drops on Building 'A' 3rd floor. Set and framed on the Steel gables for Building 'C'. Stood walls on Building 'E' and pre-fabbed floor sections for Building 'B'.
(Reliance) drilled and boxed on 2nd, 3rd, and 4th floors of Building 'C'
(Red Oak Plumbing) set the Tubs and ran DWV on 3rd floor of Building 'C'
Sub Meeting 12/10/2012
Alma (Utek)
William (Air Doctors)
Craig (Red Oak)
Jose (Warburtons)
Eric (Nutek)
Talking Points
Schedule
Building ‘A’ Finish work starts 1st floor 1/2
Building ‘A’ Paint starts 1st floor 1/4
Alma (Utek)
William (Air Doctors)
Craig (Red Oak)
Jose (Warburtons)
Eric (Nutek)
Talking Points
- (Air Doctors) will finish ducts on 2nd floor today, 4th floor tomorrow, 3rd floor Wednesday or Thursday. They will also finish the fire caulk for inspection tomorrow.
- Framers will finish framing drops tonight.
- (Extreme Fire) will finish the Attic system by end of day Tuesday 12/18 so that drywall can be hung on the 4th floor. Drywall can hang all but the North breeze way and Northern 2 units.
- (Red Oak) Will finish tubs and DWV for inspection on Thursday 12/20. Gas lines will start Thursday and 1st and 2nd floors will be complete by Thursday 12/27.
- (Nutek) will have ½ of 1st floor ready for finish carpenters by Thursday 12/20.
- In the 1x1 exterior units for Building ‘C’ 4th floor we will end the drop at the edge of the bedroom door in order to clear the attic access. William (Air Doctors) said that it will mean that the duct will end in the end of the drop and not down through the drop but that should not be a problem. Shawn (Extreme Fire) said that Fire sprinklers should not need to change.
Schedule
Building ‘A’ Finish work starts 1st floor 1/2
Building ‘A’ Paint starts 1st floor 1/4
Building ‘A’ Gypcrete 12/27-12/30
Building ‘C’ DWV inspection 12/20
Building ‘C’ 1st and 2nd Floor 4-way 12/27