Subs on Site
<Cardalls> (3)
<Warburtons> (12)
<Nutek> (7)
<Diamond Z> (3)
<Extreme Fire> (5)
<Air Doctors> (4)
<Utek> (23)
<Reliance> (6)
<Red Oak Plumbing> (4)
Work in Progress:
(Cardalls)Insulated the walls on the 4th Floor for Building 'A' and above pre-rock on the North end of 3rd floor.
(Warburtons) siding South breezeway and Soffit on Building 'A'. Siding on Building 'B' garage. Worked on the last of Building 'A' roof and Building 'C' garage roof.
(Nutek) pre-rocked the Southern units on Building 'A' 4th floor.
(Extreme Fire) worked on 3rd floor of Building 'C' and the attic in Building 'A'
(Air Doctors) started running the vents for Building 'C'
(Utek) set the steel on Building 'C' as well as the gables on them. Finished sheeting 3rd floor on Building 'E'
(Reliance) Set the interior panels and started pulling feeders on Buildng 'C'
(Red Oak Plumbing) set tubs in place on Building 'C' and walked with the inspector on Building 'A' to pass 4-way on 1st floor and pre-rock on 3rd.