Weather: Partly Cloudy 38˚/16˚
Subs on Site
<Cardalls> (3)
<Warburtons> (9)
<Nutek> (4)
<Diamond Z> (1)
<Extreme Fire> (2)
<Air Doctors> (3)
<Utek> (17)
<Reliance> (4)
<Red Oak Plumbing> (6)
Work in Progress:
(Cardalls) Insulated the walls behind the tubs and chases on Building 'C'
(Warburtons) Installed the siding and soffit on the South West corner of Building 'A' as well as the South Breezeway. Roofed Building 'A' Garage.
(Nutek) Finished hanging the 1st floor units on the South end of Building 'A' and started on the North end.
(Diamond Z) Grouted the last of the stone on the Chimneys and started laying the caps stones for he entry columns on Building 'A'
(Extreme Fire) Worked on the attic system on the North End of Building 'A'. Shawn (Extreme Fire) decided last night that we will be OK to keep going covering he fire sprinklers.
(Air Doctors) Ran exhaust Vents on Building 'C"
(Utek)finished Building 'C" roof, Started setting windows on Building 'C. Set wall sections for the 4th floor on Building 'D' and sheeted the 4th Floor on Building 'E'. They also moved their crane from Building 'C' to Building 'D'.
(Reliance) worked on Building 'C" panels
(Warburtons) Installed the siding and soffit on the South West corner of Building 'A' as well as the South Breezeway. Roofed Building 'A' Garage.
(Nutek) Finished hanging the 1st floor units on the South end of Building 'A' and started on the North end.
(Diamond Z) Grouted the last of the stone on the Chimneys and started laying the caps stones for he entry columns on Building 'A'
(Extreme Fire) Worked on the attic system on the North End of Building 'A'. Shawn (Extreme Fire) decided last night that we will be OK to keep going covering he fire sprinklers.
(Air Doctors) Ran exhaust Vents on Building 'C"
(Utek)finished Building 'C" roof, Started setting windows on Building 'C. Set wall sections for the 4th floor on Building 'D' and sheeted the 4th Floor on Building 'E'. They also moved their crane from Building 'C' to Building 'D'.
(Reliance) worked on Building 'C" panels