Weather: Clear 38˚/17˚
Subs on Site
<Warburtons> (9)
<Nutek> (5)
<Diamond Z> (1)
<Extreme Fire> (2)
<Air Doctors> (1)
<Utek> (17)
<Reliance> (4)
<Red Oak Plumbing> (6)
Work in Progress:
(Warburtons) worked on siding for the South Breeze way and the sidiing and soffit on the West center section of Building 'A'. Finished up some roofing on Building 'A's peak.
(Nutek) Hung sheetrock on the 5th of the 8 1st floor units. Started pre rock behind the tubs on Building 'C'
(Diamond Z) worked on the caps for the entry gables
(Extreme Fire) worked on the Attic system for Building 'A' and cut the sprinklers in the drop areas to the correct length.
(Air Doctors) touched up the fire caulk were needed for inspection.
(Utek)finished the roof on Building 'C'. Worked on the pick-up sheeting for Building 'A' and started the drops on the 2nd Floor. Finished standing the walls on Building 'D'. Finished Sheeting the floor on Building 'E'.
(Red Oak) set 4 of the tubs on first floor of Building 'C'. Drilled for gas on Building 'C' and started stacking the DWV.