Thursday 3/38/2013

Weather: Sunny 66˚/38˚ 

Subs on Site
<Sterns>                          (6)
<SBS>                              (4)
<Wall to Wall>                  (3)
<Nutek>                            (3)
<Cardalls>                        (5)
<Warburtons>                  (8)
<Diamond Z>                    (3)
<Air Doctors>                   (3)
<Reliance>                       (1)
<Red Oak Plumbing>       (3)

Work in Progress
(Sterns) Formed the sidewalk on the North end of Building 'A'   They had to dig out almost every spot they formed. (See Picture below)

(SBS) Finish work on 1st and then 2nd floor Building 'E'. Worked on the bath hardware of Building 'C'.

(Wall to Wall) Primed 3rd and 4th floor on Building 'D' and then painted  

(Nutek) Textured 3rd and 4th floors in Building 'E'.

(Cardalls) Insulated 3rd and 4th floor North Tower of Building 'B'.  

(Warburtons) Worked on the breezeway and South decks on 4th floor of Building 'D'.  Siding on the East side of Building 'E'.  And the entry gables on the North side of Building 'D'.

(Diamond Z) Scratch coated Building 'B' and the Clubhouse.

(Air Doctors) Trim for Building 'C'.  Line sets in 1st floor Building 'B'

(Reliance) Worked on trim in Building 'C'. 

(Red Oak) Install trim in Building 'C'. 





Wednesday 3/27/2013


Weather: Sunny 62˚/38˚ 

Subs on Site
<Sterns>                          (6)
<SBS>                              (4)
<Wall to Wall>                  (3)
<Nutek>                            (7)
<Cardalls>                        (5)
<Warburtons>                  (8)
<Diamond Z>                    (3)
<Air Doctors>                   (3)
<Reliance>                       (2)
<Red Oak Plumbing>       (3)

Work in Progress
(Sterns) Poured the first 100' of sidewalk around Building 'A' and formed the second 100' and the stairs on the South West entry.  They had to cut out and replace the ADA ramp on the South East curb.

(SBS) Finish work on 1st floor Building 'E'.  Replaced the ADA shelves in Building 'A' that were installed too low.

(Wall to Wall) Prepped 3rd and 4th floor on Building 'D' 

(Nutek) Hung pre Rock on Building 'B' 3rd and 4th floor South Tower.  Fire Taped 2nd, 3rd and 4th floor South tower in Building 'B'.

(Cardalls) Insulated 2nd and started on 3rd floor North Tower of Building 'B'.  

(Warburtons) Worked on the breezeway on 4th floor of Building 'D'.  Siding on the South side of Building 'E'.  And the entry gables on the North side of Building 'D'.

(Diamond Z) Installed lath on Building 'B'

(Air Doctors) Trim for Building 'C'.  Line sets in 1st floor Building 'B'

(Reliance) Worked on trim in Building 'C'. 

(Red Oak) Install trim in Building 'C'. Stocked their water heaters in the units for Building 'E'.

While Sterns was cutting the concrete in front of Building 'A' the smoke from the saw got into the riser room smoke detector.  The fire alarm went off.  It called the entire Uintah County fire department.




Tuesday 3/27/2013


Weather: Sunny 56˚/24˚ 

Subs on Site
<SBS>                              (2)
<Wall to Wall>                  (3)
<Nutek>                            (7)
<Cardalls>                        (5)
<Warburtons>                  (8)
<Diamond Z>                    (3)
<Air Doctors>                   (3)
<Reliance>                       (2)
<Red Oak Plumbing>       (2)

Work in Progress
(SBS) Started finish work on Building 'E'.  Replaced base boards in Building 'D' that were cut too short.

(Wall to Wall) Prepped 2nd floor and started on 3rd floor on Building 'D' 

(Nutek)Hung pre Rock on Building 'B' 3rd floor South Tower.  Taped 2nd floor in Building 'E'.

(Cardalls) Insulated 3rd and 4th floor South Tower of Building 'A'.  They sent the 3 temp workers home and brought 3 insulators up.

(Warburtons) Worked on the breezeway on 2nd then started on 3rd floor of Building 'D'.  Siding on the South side of Building 'E'.  And the entry gables on the North side of Building 'D'.

(Diamond Z) Installing lath on Building 'B'

(Air Doctors) Set Furnaces for Building 'C'.  Touched up their fire caulk in Building 'B' North tower and kept setting the hard ducts in 1st floor Building 'B"

(Reliance) Worked on trim in Building 'C'. Touched up their fire caulk in North tower of Building 'B'.

(Red Oak) Install trim in Building 'C'.  Touched up their fire caulk in Building 'B' North tower.


Monday 3/26/2013

Weather: Sunny 41˚/16˚ 

Subs on Site
<SBS>                              (2)
<Wall to Wall>                  (2)
<Nutek>                            (7)
<Cardalls>                        (5)
<Warburtons>                  (8)
<Diamond Z>                    (3)
<Air Doctors>                   (3)
<Reliance>                       (2)
<Red Oak Plumbing>       (2)

Work in Progress
(SBS) Stocked the doors in to Building 'E' and replaced base boards in Building 'D';that were cut too short.

(Wall to Wall) Prepped 2nd floor on Building 'D' 

(Nutek)Hung pre Rock on Building 'B';2nd floor South Tower.  Taped 2nd floor in Building 'E'.

(Cardalls) Insulated 2nd floor South Tower of Building 'A'.

(Warburtons) Worked on the breezeway on 2nd floor of Building 'D'.  Siding on the South side of Building 'E'.  A Highway Patrol officer came by the site to talk to the siding guys about something that happened off site.

(Diamond Z) Started installing lath on Building :B;.

(Air Doctors) Set Furnaces for Building 'B'.  Touched up their fire caulk in Building 'B' and started setting the hard ducts in 1st floor  Building 'B"

(Reliance) Worked on trim in Building 'C'. Touched up their fire caulk in Building 'B'.

(Red Oak) Spread the trim and started install  in Building 'C'.  Touched up their fire caulk in Building 'B'.







Wednesday 3/20/2013

Weather: Sunny 51˚/28˚ 

Subs on Site
<SBS>                              (4)
<Wall to Wall>                  (3)
<Diamond Z>                    (3)
<Nutek>                            (9)
<Cardalls>                        (5)
<Warburtons>                  (8)
<Air Doctors>                   (3)
<Reliance>                       (12)
<Red Oak Plumbing>       (3)

Work in Progress
(SBS) Installed hardware and unboxed appliances for Building 'C'.  They repaired 3 door stops in Building 'D' that were damaged when windows were left open and the wind blew them closed.

(Wall to Wall) Painted the patches on the 2nd and 3rd floor of the North Tower in Building 'A'. 

(Diamond Z) Worked on Building 'D&E'.

(Nutek) Hung and fire taped the under stair closets in Building 'A'..  The tapers textured 1st floor Building 'E' and fire taped the 4th floor breezeway ceilings.

(Cardalls) Insulated 1st floor of Building 'A'.

(Warburtons) Worked on the South side entry gables of Building 'C'.  Worked on the breezeway on 1st and 2nd floor of Building 'D'.  Started siding on the West side of Building 'E'.

(Air Doctors) Set and Charged the Condensers for Building 'A'.  Touched up their fire caulk in Building 'B'.

(Reliance) Worked on trim in Building 'C' and wired the condensers on Building 'A'. Touched up their fire caulk in Building 'B'.

(Red Oak) Spread the trim in Building 'C'.  Touched up their fire caulk in Building 'B'.

Aaron (Uintah County) Came to inspect the Building and issued a temporary Occupancy permit for Building 'A' 
Robert (HUD) signed off on occupancy and asked that the pressure stay on to clean the Building and Parking lot.



Tuesday 3/19/2013


Weather: Sunny 63˚/28˚ 

Subs on Site
<SBS>                              (4)
<Wall to Wall>                  (3)
<Diamond Z>                    (3)
<Nutek>                            (3)
<Cardalls>                        (4)
<Warburtons>                  (8)
<Extreme Fire>                 (2)
<Air Doctors>                   (3)
<Reliance>                       (12)
<Red Oak Plumbing>       (3)

Work in Progress
(SBS) Installed hardware and unboxed appliances for Building 'C'.  Ryan adjusted the entry doors so they self close.

(Wall to Wall) Painted the patches on the 1st floor of the North Tower in Building 'A'. 

(Diamond Z) Worked on Building 'D&E' stone and rebuilt the dumpster for Building 'A'.

(Nutek) Taped 1st floor in Building 'E'.  The tapers touched up Building 'A' North Tower..  

(Cardalls) Insulated 1st floor of Building 'A'.

(Warburtons) Worked on the South side entry gables of Building 'C'.  Worked on the South West side of Building 'D'.

(Air Doctors) Set the Condensers for Building 'A'.

(Reliance) Worked on trim in Building 'C' and wired the condensers on Building 'A'.

(Red Oak) Stocked the trim in Building 'C'.  They fixed leaks in A303 and A108..

Thursday 3/14/2013

Weather: Sunny 63˚/28˚ 

Subs on Site

<G&M Woods>                 (4)
<Wall to Wall>                  (4)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Cardalls>                        (2)
<Warburtons>                  (8)
<Extreme Fire>                 (2)
<Air Doctors>                   (7)
<Reliance>                       (12)
<Red Oak Plumbing>       (4)

Work in Progress
(G&M Woods) Installed the cabinets in Building 'C' 2nd and 3rd floors on West end.

(Wall to Wall) Painted the patches on the 4th floor of the South Tower in Building 'A'.  There were 50 in just these four units.

(Diamond Z) Worked on Building 'D&E' stone.

(Nutek) Hung finished sheetrock in Building 'E'.  The tapers touched up Building 'A' North Tower..  

(Warburtons) Worked on the South side entry gables of Building 'C'.  Worked on the North side of Building 'D'. They also finished all of the roofs.

(Air Doctors) Finished pre rough for 1st floor in Building 'B'.  They tried to set the Condencers but the pads that DG Concrete graded were not big enough. 

(Reliance) Wiring Building 'B'.

(Red Oak) Fire caulked Building 'B'  Finished the punch list on Building 'A'.



Wednesday 3/13/2013

Weather: Sunny 55˚/27˚ 

Subs on Site

<Wall to Wall>                  (4)
<SBS>                              (4)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Cardalls>                        (2)
<Warburtons>                  (8)
<Extreme Fire>                 (2)
<Air Doctors>                   (4)
<Reliance>                       (12)
<Red Oak Plumbing>       (1)
<DG Concrete>                (2)


Work in Progress
Outback Rentals came out to repair the lift and the pin that holds the new ram to the forks would not go through the bent bracket.  We are going to rent a lift for now and buy a new bracket. 

(Wall to Wall) Painted 1st floor Building 'D'.

(SBS) Worked on trim on 3rd floor of Building 'D' then started hardware in Building 'C'

(Diamond Z) Worked on Building 'E' stone.

(Nutek) Hung the sheetrock in Building 'E' 3rd floor.  The tapers touched up Building 'A' 3rd and 4th floor South end.  

(Warburtons) Worked on the South side entry gables of Building 'C'.  Worked on the North side of Building 'D'.

(Air Doctors) Finished pre rough for 1st floor in Building 'B'

(Reliance) Wiring Building 'B'.

(Red Oak) Fire caulked Building 'B'  Found and fixed another leak in Building 'A' 403. .

(DG Concrete) graded the pads for the condensers. 

Tuesday 3/12/2013

Weather: Sunny 49˚/27˚ 

Subs on Site
<SBS>                              (4)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Cardalls>                        (2)
<Warburtons>                  (8)
<Extreme Fire>                 (2)
<Air Doctors>                   (4)
<Reliance>                       (12)
<Red Oak Plumbing>       (1)

Work in Progress
(Wall to Wall) Primed 1st floor Building 'D'.

(SBS) Worked on trim on 3rd floor of Building 'D' then started hardware in Building 'C'

(Diamond Z) Worked on Building 'E' stone.

(Nutek) Hung the sheetrock in Building 'E' 4th floor.  The tapers touched up Building 'A' 3rd and 4th floor South end.  They textured 4th floor in Building 'D'.

(Warburtons) Worked on the South side entry gables of Building 'C'.  Worked on the North side of Building 'D'.

(Air Doctors) Installed the exhaust vents on the Water heaters in Building 'A'

(Reliance) Wiring Building 'B'.

(Red Oak) Fire caulked Building 'B'.  We found one a tub that would not drain in A208..



Monday 3/11/2013

Weather: Sunny 44˚/24˚ 

Subs on Site
<Wall to Wall>                  (4)
<SBS>                              (4)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Warburtons>                  (6)
<Air Doctors>                   (4)
<Reliance>                       (12)
<Red Oak Plumbing>       (1)

Work in Progress
(Wall to Wall) Prepped 1st floor Building 'D'.

(SBS) Worked on trim on 3rd floor of Building 'D'

(Diamond Z) Worked on Building 'E' stone.

(Nutek) Hung the sheetrock in Building 'E'.  The tapers did not work on Building 'A' on Thursday and Friday.  The Painters were able to start on Building 'D' while they wait to touch up Building 'A'. They will repaire Building 'A' so that the painters can touch up on Wednesday. 

(Warburtons) Worked on the West side of Building 'C' but their lift would not start today.  Worked on the East side of Building 'D'.

(Air Doctors) Worked on the flex ducts 3rd and 4th floors Building 'E' and passed inspection on 3rd and 4th floors  fire caulk.

(Reliance) Wiring Building 'B'.

(Red Oak) Past fire caulk inspection on Building 'E'.  Started fire caulking Building 'B'.  We found one more leak in unit 403.



Sub Meeting 3/11/2013

Bryson (Reliance)
Rob (Wall to Wall)
Ryan (SBS)
Eric (Nutek)

Talking Points:
Track out and Mud: Each contractor is responsible for their own track out both into the street and onto our lot.
Curbs are soft: With all of the melt the curbs are soft and I ask that no one drive over the curbs without a dirt ramp.
Heaters:  We will be turning the heaters off during the day and night unless the drywaller or painter needs them to dry.
Building ‘A’ Nutek will tape the patches and touch up for ‘A’ today and into tomorrow.  Rob (Wall to Wall) will start touch-up paint on Wednesday.
Building ‘C’  Vinyl will start on Wednesday 3/13.  They will have 2 or 3 units ready by 10 AM so that (G&M Woods) can start cabinet install on 2nd, 3rd, and 4th floors Wednesday 3/13 behind them..
Building ‘D’ 4th floor should be textured by 3/12 with sand and touch-up on Wednesday 3/13.   Finish work will be comple on 3rd floor for the painter to start by mid-day tomorrow 3/12.
Building ‘E’  Fire caulk inspection passed for 3rd and 4th floors today.  Flex ducts should be complete tonight for the entire Building.  Fire sprinklers are only trimmed in 2 ½ units on 1st floor they will try to get here tomorrow or Wednesday to cut the remainder of the Building.
Building ‘B’  Bryson (Reliance) said they will be able to have the whole of Building ‘A’ ready for 4-way Monday 3/18 and a majority for our 4-way on Thursday 3/14.  The insulators will start on Monday 3/18.  


Schedule:
Building ‘A’
Final inspection 3/13
HUD inspection 3/20
Building ‘C’
2nd, 3rd and 4th floor Vinyl 3/14
2nd, 3rd, and 4th floor Cabinets start 3/14
Building ‘D’
4th floor Drywall textured 3/13.
3rd Floor Finish work complete 3/13.
4th Floor Finish work complete 3/15.

1st and 2nd  floor Paint starts  3/11 complete 3/22.

Building ‘E’
Fire Caulk inspection 3/11.
Flex ducts installed 3/11.
Drywall starts 3/11.
Gypcrete 3/21.
Building ‘B’
4-way inspection 3/14.
Insulation starts 3/18.