Work in Progress
(Wall to Wall) Prepped 1st floor Building 'D'.
(SBS) Worked on trim on 3rd floor of Building 'D'
(Diamond Z) Worked on Building 'E' stone.
(Nutek) Hung the sheetrock in Building 'E'. The tapers did not work on Building 'A' on Thursday and Friday. The Painters were able to start on Building 'D' while they wait to touch up Building 'A'. They will repaire Building 'A' so that the painters can touch up on Wednesday.
(Warburtons) Worked on the West side of Building 'C' but their lift would not start today. Worked on the East side of Building 'D'.
(Air Doctors) Worked on the flex ducts 3rd and 4th floors Building 'E' and passed inspection on 3rd and 4th floors fire caulk.
(Reliance) Wiring Building 'B'.
(Red Oak) Past fire caulk inspection on Building 'E'. Started fire caulking Building 'B'. We found one more leak in unit 403.


Sub Meeting 3/11/2013
Bryson (Reliance)
Rob (Wall to Wall)
Ryan (SBS)
Eric (Nutek)
Talking Points:
Track out and Mud: Each contractor is responsible for their own track out both into the street and onto our lot.
Curbs are soft: With all of the melt the curbs are soft and I ask that no one drive over the curbs without a dirt ramp.
Heaters: We will be turning the heaters off during the day and night unless the drywaller or painter needs them to dry.
Building ‘A’ Nutek will tape the patches and touch up for ‘A’ today and into tomorrow. Rob (Wall to Wall) will start touch-up paint on Wednesday.
Building ‘C’ Vinyl will start on Wednesday 3/13. They will have 2 or 3 units ready by 10 AM so that (G&M Woods) can start cabinet install on 2nd, 3rd, and 4th floors Wednesday 3/13 behind them..
Building ‘D’ 4th floor should be textured by 3/12 with sand and touch-up on Wednesday 3/13. Finish work will be comple on 3rd floor for the painter to start by mid-day tomorrow 3/12.
Building ‘E’ Fire caulk inspection passed for 3rd and 4th floors today. Flex ducts should be complete tonight for the entire Building. Fire sprinklers are only trimmed in 2 ½ units on 1st floor they will try to get here tomorrow or Wednesday to cut the remainder of the Building.
Building ‘B’ Bryson (Reliance) said they will be able to have the whole of Building ‘A’ ready for 4-way Monday 3/18 and a majority for our 4-way on Thursday 3/14. The insulators will start on Monday 3/18.
Schedule:
Building ‘A’
Final inspection 3/13
HUD inspection 3/20
Building ‘C’
2nd, 3rd and 4th floor Vinyl 3/14
2nd, 3rd, and 4th floor Cabinets start 3/14
Building ‘D’
4th floor Drywall textured 3/13.
3rd Floor Finish work complete 3/13.
4th Floor Finish work complete 3/15.
1st and 2nd floor Paint starts 3/11 complete 3/22.
Building ‘E’
Fire Caulk inspection 3/11.
Flex ducts installed 3/11.
Drywall starts 3/11.
Gypcrete 3/21.
Building ‘B’
4-way inspection 3/14.
Insulation starts 3/18.