Subs on Site
<SBS> (4)
<Wall to Wall> (3)
<Wall to Wall> (3)
<Diamond Z> (3)
<Nutek> (9)
<Cardalls> (5)
<Warburtons> (8)
<Air Doctors> (3)
<Warburtons> (8)
<Air Doctors> (3)
<Reliance> (12)
<Red Oak Plumbing> (3)
Work in Progress
(SBS) Installed hardware and unboxed appliances for Building 'C'. They repaired 3 door stops in Building 'D' that were damaged when windows were left open and the wind blew them closed.
(Wall to Wall) Painted the patches on the 2nd and 3rd floor of the North Tower in Building 'A'.
(Wall to Wall) Painted the patches on the 2nd and 3rd floor of the North Tower in Building 'A'.
(Diamond Z) Worked on Building 'D&E'.
(Nutek) Hung and fire taped the under stair closets in Building 'A'.. The tapers textured 1st floor Building 'E' and fire taped the 4th floor breezeway ceilings.
(Cardalls) Insulated 1st floor of Building 'A'.
(Warburtons) Worked on the South side entry gables of Building 'C'. Worked on the breezeway on 1st and 2nd floor of Building 'D'. Started siding on the West side of Building 'E'.
(Warburtons) Worked on the South side entry gables of Building 'C'. Worked on the breezeway on 1st and 2nd floor of Building 'D'. Started siding on the West side of Building 'E'.
(Air Doctors) Set and Charged the Condensers for Building 'A'. Touched up their fire caulk in Building 'B'.
(Red Oak) Spread the trim in Building 'C'. Touched up their fire caulk in Building 'B'.
Aaron (Uintah County) Came to inspect the Building and issued a temporary Occupancy permit for Building 'A'
Robert (HUD) signed off on occupancy and asked that the pressure stay on to clean the Building and Parking lot.