Subs on Site
<SBS> (2)
<Wall to Wall> (2)
<Wall to Wall> (2)
<Nutek> (7)
<Cardalls> (5)
<Warburtons> (8)
<Diamond Z> (3)
<Warburtons> (8)
<Diamond Z> (3)
<Air Doctors> (3)
<Reliance> (2)
<Red Oak Plumbing> (2)
Work in Progress
(SBS) Stocked the doors in to Building 'E' and replaced base boards in Building 'D';that were cut too short.
(Wall to Wall) Prepped 2nd floor on Building 'D'
(Wall to Wall) Prepped 2nd floor on Building 'D'
(Nutek)Hung pre Rock on Building 'B';2nd floor South Tower. Taped 2nd floor in Building 'E'.
(Cardalls) Insulated 2nd floor South Tower of Building 'A'.
(Warburtons) Worked on the breezeway on 2nd floor of Building 'D'. Siding on the South side of Building 'E'. A Highway Patrol officer came by the site to talk to the siding guys about something that happened off site.
(Warburtons) Worked on the breezeway on 2nd floor of Building 'D'. Siding on the South side of Building 'E'. A Highway Patrol officer came by the site to talk to the siding guys about something that happened off site.
(Diamond Z) Started installing lath on Building :B;.
(Air Doctors) Set Furnaces for Building 'B'. Touched up their fire caulk in Building 'B' and started setting the hard ducts in 1st floor Building 'B"
(Red Oak) Spread the trim and started install in Building 'C'. Touched up their fire caulk in Building 'B'.