Weather: Sunny 63˚/28˚
Subs on Site
<SBS> (4)
<Wall to Wall> (3)
<Wall to Wall> (3)
<Diamond Z> (3)
<Nutek> (3)
<Cardalls> (4)
<Warburtons> (8)
<Extreme Fire> (2)
<Air Doctors> (3)
<Warburtons> (8)
<Extreme Fire> (2)
<Air Doctors> (3)
<Reliance> (12)
<Red Oak Plumbing> (3)
Work in Progress
(SBS) Installed hardware and unboxed appliances for Building 'C'. Ryan adjusted the entry doors so they self close.
(Wall to Wall) Painted the patches on the 1st floor of the North Tower in Building 'A'.
(Wall to Wall) Painted the patches on the 1st floor of the North Tower in Building 'A'.
(Diamond Z) Worked on Building 'D&E' stone and rebuilt the dumpster for Building 'A'.
(Nutek) Taped 1st floor in Building 'E'. The tapers touched up Building 'A' North Tower.. .
(Cardalls) Insulated 1st floor of Building 'A'.
(Warburtons) Worked on the South side entry gables of Building 'C'. Worked on the South West side of Building 'D'.
(Warburtons) Worked on the South side entry gables of Building 'C'. Worked on the South West side of Building 'D'.
(Air Doctors) Set the Condensers for Building 'A'.
(Red Oak) Stocked the trim in Building 'C'. They fixed leaks in A303 and A108..