Subs on Site
<Sterns> (6)
<SBS> (4)
<Wall to Wall> (3)
<SBS> (4)
<Wall to Wall> (3)
<Nutek> (3)
<Cardalls> (5)
<Warburtons> (8)
<Diamond Z> (3)
<Warburtons> (8)
<Diamond Z> (3)
<Air Doctors> (3)
<Reliance> (1)
<Red Oak Plumbing> (3)
Work in Progress
(Sterns) Formed the sidewalk on the North end of Building 'A' They had to dig out almost every spot they formed. (See Picture below)
(SBS) Finish work on 1st and then 2nd floor Building 'E'. Worked on the bath hardware of Building 'C'.
(Wall to Wall) Primed 3rd and 4th floor on Building 'D' and then painted
(SBS) Finish work on 1st and then 2nd floor Building 'E'. Worked on the bath hardware of Building 'C'.
(Wall to Wall) Primed 3rd and 4th floor on Building 'D' and then painted
(Nutek) Textured 3rd and 4th floors in Building 'E'.
(Cardalls) Insulated 3rd and 4th floor North Tower of Building 'B'.
(Warburtons) Worked on the breezeway and South decks on 4th floor of Building 'D'. Siding on the East side of Building 'E'. And the entry gables on the North side of Building 'D'.
(Diamond Z) Scratch coated Building 'B' and the Clubhouse.
(Air Doctors) Trim for Building 'C'. Line sets in 1st floor Building 'B'
(Red Oak) Install trim in Building 'C'.