Weather: Sunny 56˚/24˚
Subs on Site
<SBS> (2)
<Wall to Wall> (3)
<Wall to Wall> (3)
<Nutek> (7)
<Cardalls> (5)
<Warburtons> (8)
<Diamond Z> (3)
<Warburtons> (8)
<Diamond Z> (3)
<Air Doctors> (3)
<Reliance> (2)
<Red Oak Plumbing> (2)
Work in Progress
(SBS) Started finish work on Building 'E'. Replaced base boards in Building 'D' that were cut too short.
(Wall to Wall) Prepped 2nd floor and started on 3rd floor on Building 'D'
(Wall to Wall) Prepped 2nd floor and started on 3rd floor on Building 'D'
(Nutek)Hung pre Rock on Building 'B' 3rd floor South Tower. Taped 2nd floor in Building 'E'.
(Cardalls) Insulated 3rd and 4th floor South Tower of Building 'A'. They sent the 3 temp workers home and brought 3 insulators up.
(Warburtons) Worked on the breezeway on 2nd then started on 3rd floor of Building 'D'. Siding on the South side of Building 'E'. And the entry gables on the North side of Building 'D'.
(Diamond Z) Installing lath on Building 'B'
(Air Doctors) Set Furnaces for Building 'C'. Touched up their fire caulk in Building 'B' North tower and kept setting the hard ducts in 1st floor Building 'B"
(Red Oak) Install trim in Building 'C'. Touched up their fire caulk in Building 'B' North tower.