Weather Sunny 87˚/54˚
Subs on Site
<DG Concrete> (6)
<Horrocks> (1)
Work in Progress:

Ben (Horrocks) came and passed the compaction of the exterior footings compaction. Ben (Horrocks) retested the sewer back fill compaction after Mike (DG Concrete) back filled with dry native soil in smaller lifts with the rolling wheel, on his track hoe, followed with the smooth roller on top. The test is still at 89% and the best test was at the driest moisture

Shad (DG Concrete) added the structural fill for the interior footings on Building 'A'. Ben (Horrocks) will return tomorrow for a final compaction test on the interior footings