Wednesday 5/23/2012


Weather Sunny & Windy 71˚/38˚


Subs on Site
<DG Concrete> (7)

Work in Progress:
Shad (DG Concrete) graded the garage pad to 8" below finish floor.  Then we laid out the footings and he dug, back filled and compacted 1/2 of them.

Chris (DG Concrete) finished the sewer laterals to each building but ran short of pipe on building 'C'.  He ran to Mountain Land and grabbed more pipe and finished all the laterals.  The water table is right near the sewer depth at the Building 'B' and Building 'D' manhole.

Tim (DG Concrete) back filled the main sewer with the new fill material
up to the Clubhouse

Patrick (DG Concrete) dug up the temp power and internet wires, while scooping the structural fill with a front loader.  I ran to Lowes grabbed wire, wire nuts, tape and spliced it.