Thursday 5/17/2012



Weather Sunny 80˚/49˚

Subs on Site
<DG Concrete> (6)

Work in Progress:
Ben (Horrocks) came and passed the compaction of the exterior footings compaction.  Ben (Horrocks) tested the sewer back fill compaction after Mike (DG Concrete) back filled with dry native soil in lifts with the rolling wheel, on his track hoe, followed with the smooth roller on top.  It tested a 88% and a little wet.
Chris (DG Concrete) laid sewer up to and just past the manhole for the Clubhouse.  Then started up the main road.