Weather Sunny 82˚/49˚
Subs on Site
<DG Concrete> (6)
<Ram Builders> (1)
<Red Oak> (2)
Work in Progress:

Ben (Horrocks) came and preformed compaction tests on the upper footings native soil, our sewer back fill, and the undisturbed native soil for a reference. Nick (M-13) is going to go over the soils report with Bill (Geo Tech) to discuss what will be required for bridging the road.
Chris (DG Concrete) heard water in the sewer line and suspected a leak. Dusty (Maeser) broght over his camera truck down and discovered a joint leaking. Chris (DG Concrete) dug up the pipe back to the leaking joint (Five lengths back) and hooked a choker on the track hoe and pulled it closed. (DG Concrete) set the first manhole and laid pipe to the second manhole and set it.

Charlie (Red Oak) noticed a discrepancy on the plans. Were the breezeway footings are under the interior footing detail(2/S1.2) and not frost protected like detail(6/S1.2). Nick (M-13) called and left a message with Shaun (AE URBIA).

(First manhole)
(Second manhole)