Tuesday 5/22/2012


Weather Sunny & Windy 87˚/53˚


Subs on Site
<DG Concrete> (6)
<Legend>          (1)
<Horrocks>       (1)


Work in Progress:
Chris (DG Concrete) Finished the sewer main line and started on laterals on Building 'A'.  


Tim (DG Concrete) started back filling the trenched at the south west property line.  


Shad (DG Concrete) finished the structural fill for the interior  footing of Building 'A' and noticed that the breeze way was not wide enough on one side.  He corrected it.


Jason (Legend) surveyed the sewer laterals, garage for building 'A', the corners for Building 'C' for rough grade, and the curbs of the long parking lot between Building 'C' and 'B'.  He will return next week on Tuesday to survey the water line.


Ben (Horrocks) passed all footings in building 'A' and the sewer trench up to the bottom manhole.  He is preforming a gradation test for the new fill material (DG Concrete) is using to back fill the trenches.