Thursday 2/28/2013


Weather: Sunny  30˚/12˚ 

Subs on Site
<Wholesale Flooring>      (7)
<SBS>                              (8)
<Diamond Z>                    (2)
<Nutek>                            (11)
<Sterns>                           (3)
<Extreme Fire>                 (4)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Red Oak Plumbing>       (6)


Work in Progress
(Wholesale Flooring) Installed carpet on the 3rd floor of Building 'A' and tack strip and pad on 4th floor.  I walked into one of the 2x2 units and noticed that the entry vinyl had a weird angle on it.  Lance and I discussed it and what the easiest fix would be as well as how much work it would take.  I called Nick and he confirmed that we needed to change   it.

(SBS) Trimed in the units on the East side of the 3rd floor of Building 'C', worked on hardware and unboxed all of the appliances for Building 'A'. 

(Diamond Z) Continued to lay stone on the South West side of Building 'E'.
(Nutek) Sanded the texture in West tower 4th floor of Building 'C'.  Hung drywall pre-rock on the 1st floor of Building 'E'.  Taped the 2nd floor of Building 'D'

(Sterns) Poured the dumpster pad and both of the temporary ramps to Building 'A'.

(Extreme Fire) Worked on Building 'B's attic system.  Passed inspection on Building 'B' plastic system. Tried a flow test  during our Fire alarm inspection but the underground was frozen and did not flow enough.   
.
(Warburtons) Worked on the North side of Building 'C' and the 4th floor East breezeway.  They started on the South side of Building 'D'

(Air Doctors) Installed trim on the North Tower of Building 'A'.  Started the Hard ducts on 1st floor Building 'E' . 

(Reliance) Installed the parking lot lights for Building 'A'.  Programmed the fire alarm system and passed inspection for Building 'A'.

(Red Oak) Finished Installing trim on the South tower Building 'A' and started on the North tower.  They also started running gas on the Club House.