Subs on Site
<Sterns> (5)
<Wall to Wall> (1)
<Wall to Wall> (1)
<Nutek> (6)
<Warburtons> (8)
<Air Doctors> (3)
<Air Doctors> (3)
<Reliance> (3)
Work in Progress
(Sterns) Formed the mailbox pad for Building 'A'. Formed for the corridors and decks for Building 'E'.
(Wall to Wall) Hung the doors on Building 'D' and then painted the inside of the door frames on Building 'A'
(Wall to Wall) Hung the doors on Building 'D' and then painted the inside of the door frames on Building 'A'
(Nutek) Taped the corridors in Building 'A'. Pre Rocked the 2nd floor in Building 'B'
(Warburtons) Siding on the East side of Building 'E'. And the entry gables on the North side of Building 'E'.
(Air Doctors) Trim for Building 'C'. Finished the hard ducts for the South Tower Building 'B'
Sub Meeting/ 4/1/2013
Rick (Warburtons)
Jared (Reliance)
Lenny (Air Doctors)
Chris (Nutek)
Talking Points:
Building ‘C’ Clean up- Every contractor needs to clean Building ‘C’
Track out and Mud: Each contractor is responsible for their own track out both into the street and onto our lot.
Building ‘A’ The Property Manager gave us a punch list for the North Tower.
Building ‘C’ Electrical trim in the untis will be complete my 4/1. Carpet install will start Wednesday 4/3. Handrails and chimney caps Monday 4/8.
Building ‘D’ Vinyl installed 4/3. Cabinet install will begin on Wednesday 4/3. Appliances delivered on 4/11.
Building ‘E’ Corridors and patios poured 4/2. Finish work on 2nd floor complete on 4/2. 3rd and 4th floors by 4/6. Paint starts 4/8 complete by 4/12. Cabinets delivered 4/15.
Building ‘B’ Fire caulk inspection for 1st floor and 2nd, 3rd, and 4th floors on the South Tower will be tomorrow. Pre Rock on 2nd, 3rd, and 4th floors in the North tower will be complete Wednesday 4/3. Drops will be framed on the 1st floor on 4/2.
Schedule:
Building ‘A’
Punch List items.
Building ‘C’
Clean Building.
Electrical trim in untis complete by 4/3.
Carpet install 4/3-4/6.
Building ‘D’
2nd, 3rd, and 4th vinyl installed 4/3
Cabinets installed 4/3-4/10
Appliances delivered 4/11
Building ‘E’
Finish Work complete 4/6
Paint 4/8-4/12
Cabinets delivered 4/15
Building ‘B’
Fire caulk inspection 1st floor and South Tower 4/2.
Pre-rock on North Tower complete 4/3.
Fire caulk inspection North Tower 4/4.
Hard Ducts on North Tower complete 4/4.
1st floor Drops framed on 4/2.